|

MAY
2010
ISSUES:
A
city with two souls
THE
much-touted Prime Minister’s Housing Scheme (PMHS) is heading for
doom. The housing minister disclosed recently that the government had
signed 36 MoUs with a number of foreign construction companies but none
had so far begun work on the project aiming for one million ‘low-cost’
housing units completed at a cost of Rs40bn.
Insecurity has been cited as the main factor for the reluctance of
foreigners to bring their investment to Pakistan.
But the PMHS was a still-born scheme. Our planners failed to understand
the implications of a scheme not based on ground realities. In a country
where the housing backlog is calculated at seven million — a figure
which grows by 500,000 every year — how far would a million housing
units built in an unspecified period take us?
According to experts the cost of Rs40bn for a million houses is itself
unrealistic. The construction cost of each house will be much higher and
with the House Building Finance Corporation now being inducted to give
loans these houses will be beyond the reach of the low-income
classes.
With the government refusing to take a hard look at the realities,
unscrupulous, avaricious and ruthless elements have stepped in as
happens in any sector where basic needs are not met legally.
The poor are being provided land that has been encroached upon by land
mafias which have grown in size. Take the case of Karachi where the
influx of immigrants from upcountry is estimated at some 30,000 families
every year. They need shelter. The natural growth rate also creates a
demand for housing.
It is ironical that the government which had pledged roti, kapra aur
makan to the voter has been turning a blind eye to this unmet need.
Worse, the parties constituting the coalition government are accused of
having become land grabbers to fulfil this need for shelter which could
have been done through legal means as holders of office.
By choosing not to do so, they have made the state the primary loser
while the principles of town planning have had to be set aside. And who
wins? The parties that rule. They are state actors who are using their
control over sectors of the state administration, such as the police, to
facilitate the illegal seizure of land.
Parveen Rehman, director OPP-RTI (Orangi Pilot Project–Research and
Training Institute), has all the facts and figures at her fingertips.
She tells me that since 1996 when Karachi began expanding spatially —
the new sabzimandi project was undertaken on the Super Highway and work
on the Northern Bypass began — land grabbing became big business in
the metropolis.
The 1,500 or so goths that had previously been on the periphery of the
city found themselves engulfed by the rolling tide of urban expansion.
They became easy victims.
The size and scale of this phenomenon is not realised and goes
unreported. Only when there is a problem — as in 2006 when Juma Goth
and Sikander Goth were seized — the matter figures in the media.
According to Parveen Rehman, 3,000 acres of land subdivided into 100,000
plots valued at Rs25bn is sold every year in the goths.
This is bound to become an explosive issue some day. It is resulting in
an unplanned change in land use that is distorting Karachi’s civic
planning — whatever there is of the latter. Obviously this will make
Karachi a more difficult place to live in.
And who are the land grabbers who are having such a field day? Ms Rehman
identifies them: 1) experienced land suppliers; 2) coercive land
grabbers; 3) goth elders who own the village; 4) members of political
parties.
How does this illegal activity proceed? Parveen Rehman describes it
graphically as she is in touch with the goth residents and has observed
the phenomenon closely. Those experienced in this business go about it
quietly. They simply purchase huge chunks of land in the goths,
subdivide them into smaller plots and sell them.
About a third of this land is taken by the homeless to put up a shelter.
The remaining two-thirds go to speculators who push up land prices. The
coercive land grabbers are the ones who use force. They may pay for some
land and occupy another chunk through violent means.
Crushed in between the two, the goth elders describe the first as the
‘peela saanp’ (a benign snake) and the second as the ‘kala saanp’
who attacks and kills. They feel discretion is the better part of valour
and make peace with the first and earn some money in the process. The
party workers just grab land where they feel they can with the backing
of their party and various government agencies. They face practically no
hurdle except when the local people resist.
Given the large number of people who have their share in the deal, the
original owner gets barely a third of the amount paid. Thus a new
category of un-regularised land is emerging.
Although over 72 per cent of the katchi abadis in Karachi had been
notified in 1985 — the period up to 1997 has also been covered under
the new notification law — the city fathers cannot sit back and plan
the metropolis. There is too much activity on the ground that is
changing land use.
This is land-grabbing of a new kind. Its features are disturbing. One is
the size of the operation. The other is the power and reach of those
involved. The victims are the impoverished who lack political clout and
influence to stop such activity peacefully.
Hence when matters get unbearable they try to resist and invariably
violence results creating a law and order situation. Not that land
grabbers do not try to touch the affluent areas. But the rich have their
connections and know how to protect themselves. What is emerging is a
city with two souls — the Karachi of the rich and the Karachi of the
poor.
(By
Zubeida Mustafa, Dawn-7, 12/05/2010)
Resolving
the energy crisis
The
total installed power-generation capacity in Pakistan is about 20,000
MW. At any point in time, only about 75 per cent of it is operational.
Pakistan`s demand is around 15,000 MW. The operational capacity and
demand seem to match. Why is it, then, that we are only able to produce
a little over 10,000 MW these days, to suffer the huge load-shedding and
industry closures?
There are a variety of factors. Pakistan`s hydel sources have the
potential to generate the 6,000 MW, but they are not producing more than
2,200 MW due to the water shortage. Gas shortages for IPPs and Gencos
have resulted in another 1,000-MW shortfall. The circular debt owed to
power producers, oil marketing companies and gas utilities is another
factor.
From 2002 to 2007, Pakistan`s annual GDP growth averaged seven per cent,
per-capita income and exports more than doubled. But while the economic
planners were doing a good job, the energy planners of that government
could not keep pace. Under the new government, which blames the previous
government for all the country`s ills, the only energy policy we have
seen is rental power plants (RPPs). This policy has been declared
non-transparent and incapable of meeting the shortages of power by the
Asian Development Bank.
All the ten new IPP plants currently being commissioned were financially
closed during the last government, despite the fact that the IPP policy
of that time left the entrepreneur at the mercy of NEPRA for tariff
determination. The IPP policy of the PPP government in the mid-1990s
might be considered non-transparent, but the fixed tariff basis on which
proposals were solicited is something we should move towards. Six
hydroelectric power plants on which work is in progress started in the
previous government. Five of them are in the public sector.
A flawed policy of the last two decades was successive governments
disallowing WAPDA to upgrade its existing generation infrastructure or
set up new power plants, while waiting for it to be privatised. This,
coupled with an inadequate IPP policy and lack of political will to
start large hydroelectric projects, has landed us in the current state
of affairs.
The RPPs were supposed to generate 2,250 MW of very expensive energy.
To-date, not one MW has come on line. The government has not formulated
any plan to utilise the vast Thar coal resources. Nor has it made an
effort for additional gas production. Not a single project in thermal,
gas, coal and hydel power generation or development of primary energy
sources has been initiated by this government.
Meanwhile, there has been no progress towards trans-national pipelines
(from Iran, Turkmenistan or Qatar). India at first manoeuvred its way
into the Iran-Pakistan-India (IPI) pipeline project, to use it for
extracting the civil nuclear power deal from the US. Now that it is no
longer interested in this pipeline deal, Pakistan has been pushed back
by at least five years in the completion of this project. The US has now
publicly advised Pakistan to drop the IPI gas pipeline.
The previous government brought together the world`s leading energy
consultants to work on the Mashal LNG project. It floated the integrated
project, which would have provided LNG on a long-term basis and
eventually have resulted in an LNG terminal in Pakistan. Two major
international LNG players came forward. After proper consideration, one
bidder was recommended. For over two years, the new government has
failed to award this project and is still sitting on it, even as the
country suffers enormous gas shortages.
What the government did do eventually was to issue a tender for
short-term purchase of LNG. Nowhere in the world is LNG sold or
purchased through such tenders. In 2007, the LNG market was a buyer`s
market and if the new government had awarded the contract, considerably
cheaper LNG could have been available in Pakistan. This act of the
government has undermined the entire LNG project.
Even after the Supreme Court decision nullifying this contract, we would
be lucky if global LNG companies are still be interested in Pakistan.
Without such supplies we are clearly heading for gas load-shedding,
which will be worse than the load-shedding the country is facing now.
What is required now is to have an optimum energy mix based on
maximisation of indigenous coal and hydel power generation. Priority
should also be placed on renewable energy sources like wind and solar
energy, particularly in remote and rural areas.
The country`s current energy mix is: oil, 31 per cent; natural gas, 51
per cent; coal, 5 per cent, hydroelectric power, 12 per cent; and
nuclear power generation, 0.7 per cent. What we should strive for is:
oil, 20 per cent, natural gas, 51 per cent; coal, 15 per cent, Hydel 20
per cent; nuclear power generation, 4 per cent; and renewable sources, 1
per cent.
Optimal capacity utilisation from IPPs must be ensured. The IPPs set up
in the mid-90`s are beyond the front loading periods of their tariffs.
Also, the more the power is purchased from them, the lower will be the
tariff. The popular belief is that Thar coal is of inferior variety. But
technology exists in the world where such coal can not only produce
energy but also, in the process, natural gas. At the same time, the
brackish water in the Thar area can be converted into potable water
during the process. Up to 10,000 MW can eventually be generated from
Thar coal.
Every sugar mill in Pakistan is capable of producing energy which can be
sold to PEPCO, based on a process called co-generation. Co-generation
uses technology where bagasse, a by-product of sugar manufacturing, and
coal can be used to generate energy. As a modest estimate, 2000 MW can
be added to the system through this source. The tariff for such energy
projects should be attractive enough for entrepreneurs and financial
institutions to finance them.
Pakistan has an estimated hydel potential of close to 50,000 MW. Only a
little over 6,000 MW has been installed. The big dams in the pipeline
are Basha, Bunji and Dasu. Pakistan should have built a big dam every
decade. Mangla was built in the 1960s and Tarbela in the 70s.
Unfortunately, in the last three decades not a single big dam has come
into existence. If the various political parties of this country can
arrive at a consensus on as controversial an issue as renaming of NWFP,
could they not have reached a consensus on Kalabagh? One large dam is
required just to overcome the losses due to silting in the existing
dams. More dams would enhance the water storage capacity of the
country.
Almost 8,000 MW can be generated through small/medium hydroelectric
units on rivers and canals. Pakistan has developed good capability of
nuclear energy both for peaceful and strategic purpose. We must explore
ways and means of increasing the share of nuclear energy from 0.7 per
cent to 4 per cent per year. Seeking a civilian nuclear energy agreement
from the US should be our top priority.
All the water and power sector projects like Gomal Dam, the raising of
Mangla, the Thal Floodwater Canal, Kachhi Canal, Rainee Canal, Satpara
Dam, Kurram Tangi Dam, Mirani Dam, Sabazkai Dam, Jinnah Barrage, Allai
Khawar, Khan Khawar, Duber Khawar, Malakand III and Neelum Jhelum Hydro
Electric Projects, were initiated during the last government. There are
a number of other sites, in various stages of study, for water
reservoirs and power generation, both on the Indus and Jhelum Rivers,
and off-channel, which should be pursued vigorously. Also, there are
small and medium storage sites in all provinces of Pakistan which must
be pursued. But all this needs vision and capacity in a
government, which is not to be seen anywhere at present. The
writer, a former federal minister, is secretary general of the Pakistan
Muslim League-Q.
(By
Humayun Akhtar Khan, The News-6, 13/05/2010)
Delay
in K-IV plan may lead to water riots
Work
on the Greater Karachi Water Supply Scheme-IV, commonly known as K-IV,
has already been delayed by two years as the Karachi Water and Sewerage
Board has not yet been given the right to draw an additional quota of
1,200 cusecs (600 million gallons daily) of water required for the
project from the Indus. KWSB officials fear that any further delay in
initiating the project might lead to water riots in 2011, if not in the
next two to three months, when summer will be at its peak.
The officials hold jointly responsible the Indus River System Authority
(Irsa) and the federal and Sindh governments for the inordinate delay in
initiating the K-IV, accusing them of a lukewarm response to its request
for the allocation 600mgd of water from the Indus.
Senior KWSB officials, seeking anonymity, said that at a time when the
utility was supplying water to 90 per cent localities of the city hooked
to its system on alternate days and that, too, mere 25 gallons per
person as against the World Health Organisation’s prescribed standards
of 45 gallons per person, any further delay in initiating the project
would create immense difficulties for them in meeting the city’s water
needs in 2011, when its population, according to the Karachi Strategic
Development Plan-2020, would surge to over 18.52 million.
The entire K-IV project is of 600mgd and its first phase of 150mgd was
to be initiated in 2008 and completed by 2011. But since the issue
concerning allocation of additional 1,200 cusecs of water from the Indus
for the project has become a game of ping pong between Irsa, the federal
government and the Sindh government, KWSB high officials forsee water
riots in 2011, if not this June and July when the demand for water would
increase considerably owing to the hot and sultry weather.
Well-placed sources told Dawn that on the one hand, both the Irsa/federal
government and provincial government were not showing any interest in
getting the additional water quota from the Indus source approved for
the city’s vital K-IV project and, on the other, even the KWSB top
bosses seemed reluctant in taking up the matter at different forums
despite knowing that any further delay in initiating the K-IV project
might create water crisis in the city in 2011 if not in the
fast-approaching summer.
As the KWSB had already utilised its quota of 1,200 cusecs (600mgd) with
the commissioning of the 100mgd K-III project in 2006, Irsa through the
federal government had been approached by the city government to seek
the right of drawing additional 1,200 cusecs of water from the Indus for
its K-IV project. The KWSB had earlier got the right of drawing 1,200
cusecs of water from the Indus during the era of Gen Zia-ul-Haq.
However, Irsa/federal government while refusing to allocate a separate
quota of water for the city from the Indus on the plea that the federal
government allocates share of water from the river on a provincial basis
and, as such, the KWSB should seek its required quota of water from the
Sindh government’s share of the Indus.
But when the previous Sindh government was approached by the KWSB with a
request to allocate the additional 1,200 cusecs of water of its share
from the Indus, the sources said the then provincial government refused
bluntly, saying that the provincial quota of water from the Indus was
already not enough to meet its drinking and agricultural
requirements.
The well-placed sources pointed out that although former city nazim Syed
Mustafa Kamal, who was also the chairman of the KWSB, in his attempt to
get the additional quota of 1,200 cusecs for the K-IV project had even
sent a summary of the project to Asif Ali Zardari through a close friend
of the president with a request to include the project in the Karachi
Package by getting it approved from the Executive Committee of the
National Economic Council (Ecnec) on a priority basis so that the city
could meet its water needs beyond 2011, nothing has, so far, been done
in this regard.
“In fact, the KWSB bosses too have failed to forcefully plead its case
to get the additional quota of 1,200 cusecs for the much-needed project
from the Indus source with Irsa/federal government and even with the
Sindh government,” the sources said. “Had the utility’s officials
convinced Irsa/federal government and Sindh government that it will not
be drawing the entire quota of 600mgd in one go but in four different
phases and that too in a period of 10 years, they would have already got
the right to draw the required quota of water from the Indus by now.”
Elaborating, they said that though the entire project required 600mgd,
it had to be completed in fours different phases and the KWSB would
initially draw only 150mgd of water in 2011 when the project’s first
phase was scheduled to be completed while the remaining quota of water
was supposed to be drawn in the next nine years as three other phases,
each to take three years, are scheduled to be completed by 2020.
Asked about the present status of the project, sources said that the
water utility’s officials concerned had consumed more than enough time
in completing the project’s study and PC-1 and it was now lying with
the Ecnec for approval.
The sources were, however, optimistic that once the project was approved
by Ecnec, the lingering issue relating to the additional quota of 1,200
cusecs from the Indus source would also be resolved amicably.
They also hoped that Ecnec would approve the K-IV project on a priority
basis keeping in view of the city’s water needs beyond 2011 as well as
its cost which had already gone up by billions of rupees since the
project was conceived and when the dollar was equal to Rs60.
(By
Azizullah Sharif, Dawn-13, 02/05/2010)
Anomalies
detected in $40m coastal community project
Auditors
have found irregularities of millions of rupees in the Sindh Coastal
Community Development Project during the period from January 2007 to
February 2010, Dawn has learnt. Highly placed sources said an audit
of the $40 million project, designed for the development of coastal
communities, found gross mismanagement of resources.
According to the audit report, there was only 16 per cent physical
progress in nearly half of the total estimated time allocated for the
project. The cumulative disbursements stood at six per cent, contract
awarded were 33 per cent and almost 77 per cent of the incremental staff
positions were vacant, the report said.
The Sindh Coastal Community Development Project is jointly funded by the
Asian Development Bank ($36 million), the Sindh government ($3.42
million) and beneficiaries ($0.65 million).
The
report prepared by Sindh Audit Director-General Nazeer Seehar found that
if the implementation schedule was not followed, targets could not be
achieved and the poor coastal communities for whom the project had been
designed would not get its benefits.
The costal community development project was to be implemented through
two consultants – the International Union for Conservation of Nature (IUCN)
to plant 3,000 hectares of mangroves at a cost of Rs44 million and the
National Rural Support Programme (NRSP) to establish around 1,300
community organisations for carrying out Rs976 million development works
– selected by the ADB.The auditors observed that the consultants were
selected on a single source selection basis without placing
advertisements in the local or international media as well as on the
internet, showing that there was a lack of competition, which was not
completely in line with the ADB’s guidelines.
The audit report found that the NRSP Badin office transferred Rs125
million to its head office in Islamabad on July 9, 2009 without getting
its approval of the project director.
Referring to the appointment and remunerations of project directors, the
report stated that rules were violated in payment of salaries to the two
project directors.
An officer who had retired in BPS 19 was appointed project director on
Dec 28, 2006 for one year. Keeping in view the officer’s grade, his
monthly salary according to government rules should have been fixed at
Rs75,000. However, the project director was given a salary package of
Rs150,000 a month. This way the payment made in excess was Rs900,000
during the year, the report said, seeking its justification.
In November 2008, the incumbent project director was appointed.
According to the audit report, although terms and conditions of his
service have not been finalised, the project director has been getting
Rs50,000 every month in excess to what government rules say about the
salary of a grade 20 officer if reappointed after retirement. Being an
officer who claimed to have retired in a basic pay scale equivalent to
grade 20, his monthly remuneration should have been fixed at Rs100,000.
However, he was appointed at a monthly salary of Rs150,000 in violation
of relevant rules. He had been paid Rs800,000 in excess from November
2008 to February 2010, the report pointed out, stating that the extra
payment needed to be justified.
The auditors found that a double-cabin vehicle (GS-7710) was allotted to
the adviser to the chief minister on the Sindh Coastal Development
Authority despite the fact that the project did not allow such privilege
for the official.
The funds spent on the repair of the vehicle and fuel amounted to
Rs381,126 so far, the report noted. The auditors recommended that the
vehicle and the amount spent on it be recovered from the adviser.
The audit report said that under the government rules the amount in
excess of even Rs200 should be paid through a “crossed cheque” but
over Rs13.9 million had been paid through bearer cheques and that also
without any acknowledgements.
The coastal forest division of the Sindh forest department, working on
behalf of the Sindh coastal community development project (SCCDP), had
made various payments – including at least six payments of over Rs2
million each between April and September 2009 – through bearer cheques.
The auditors said that payments done in this manner were irregular as
even acknowledgement receipts were not shown to them despite repeated
requests.
The auditors noted that the Sindh Rural Development Programme (SRDP),
which had agreed to give 10 double-cabin vehicles to the SCCDP, had only
provided four vehicles whereas it transferred a single-cabin vehicle to
its Islamabad head office. The report recommended the SRDP to provide
the remaining six vehicles to the SCCDP and bring back the vehicle from
the head office.
Although the posts of conservator of forests and divisional forest
officer had not been allocated in the project, the SCCDP hired services
of two forest department officials – Riaz Wagan and Agha Tahir – on
deputation in February 2009, which according to the audit report was
irregular and unjustified.
The audit pointed out that the NRSP appointed more than 90 staffers,
including over 50 of its employees, without consultation with the
authority or setting any competitive criteria. The agreement between the
NSRP and the Coastal Development Authority (CDA) clearly mentions that
“project staff selection process shall be transparent and competitive
and the key staff to be engaged by the consultants will be evaluated by
the clients (CDA).”
The auditors also called for the recovery of Rs666,000, paid to SCDA
staffers as project allowance against the guidelines prescribed by the
donor.
The NRSP Badin office purchased furniture, fixtures, a camera and other
material at a cost of over Rs1.735 million without inviting open
tenders, which was a clear violation of the public procurement rules. In
other cases, it purchased computers and accessories by inviting bids,
but instead of accepting the lower bids the NRSP accepted higher bids
and spent over Rs134,000 extra. The auditors said that the
responsibility of the irregularity should be fixed.
Some 23 regular staffers – 18 from the forest department and five from
the livestock department – were hired by the project without open
competition. They were being given the project allowance, which was to
be given only when a government servant was hired through an open
competitive process. Otherwise, the rules said they should be paid
deputation allowance only.
The International Union for Conservation of Nature, the Coastal
Development Authority’s consultant, spent over Rs1.357 million between
April and December 2009 under various heads such as fuel expenses,
labour charges, rent, and other miscellaneous charges. However, these
expenditures were shown under the head of “trainings/ seminar/
workshop” without re-appropriation orders so this expenditure was
misclassified and irregular, the auditors observed.
The audit has noted that both consultants, the NRSP and the IUCN, were
not maintaining proper record of the funds, which they had received
directly from the ADB, in shape of cashbooks and ledger books.
When asked by the auditors the NRSP provided partial information – the
bank statement – while in the case of the IUCN no record was found to
be maintained separately. The agreement clearly mentioned: “The
consultant shall keep accurate and systematic accounts and records in
respect of the services hereunder, in accordance with internationally
accepted accounting principles …”
Speaking to Dawn, Sindh Audit Director-General Nazeer Seehar said the
records of investigation conducted by the ADB on the complaint about the
selection of project director and the approval of the Single Source
Selection (SSS) criteria for appointment of consultants was not provided
to the audit for scrutiny. He said Section 14 (3) of the Auditor General’s
(functions, powers, and terms and condition of Service) Ordinance 2001,
clearly states that “any person or authority hindering the audit
functions of the auditor general regarding inspection of accounts shall
be subject to disciplinary action under Efficiency and Discipline Rules.”
(By
Bhagwandas, Dawn-13, 06/05/2010)
Freeing
education
Though
much attention has been paid by the media to the various clauses of the
18th Amendment, the guaranteeing of the right to education in the newly
enacted Article 25A of the Constitution has not received little
meaningful coverage. The right to education has been considered
fundamental in the Constitution under Articles 9, 14, 18, 20 and 22 in
the pre-18th Amendment era.
As no explicit clause guaranteeing the same had ever been included in
the constitution prior to the 18th Amendment, the courts addressed the
issue by widening the ambit of the right to life under Article 9, taken
together with other articles, to include the right to education. As
such, it was stated that in order to be able to sustain a minimum
standard of living, to uphold your right to life, a certain level of
education was necessary. This implicated Articles 14, 18, 20, and 22,
which elaborate upon issues of the dignity of man, the right to trade or
to carry on a lawful profession, the right to manage one’s religious
institutions of teaching, and pertinent safeguards in respect to
religion in educational institutions.
Along with these articles, Article 37 of the Constitution was often
mentioned as it sys the state shall provide free and compulsory
education to its citizens at the earliest, subject to the availability
of resources. However, the latter provision is within the Principles of
Policy section of the Constitution which, vide Article 30, is not
enforceable by any court of law in Pakistan. The courts therefore have
seldom questioned the policy decisions made by the government with
regard to education, unless they were made in unfair exercise of
authority.
However, in defining the tight to education, the Supreme Court in 2000
SCMR 1222 has said that the "right to seek admission in an
educational institution and to continue studies therein was always
subject to the rules of discipline prescribed by the institution, and
therefore, a student who intended to pursue his studies in the
institution was bound by such rules." Furthermore, the Sindh High
Court in 2007 PLD Kar 116 stated that any "unreasonable restraint,
hindrance or condition on its (the right to education) exercise would be
ultra vires [a violation of] the Constitution".
This seems to have been further elucidated in several cases, including
two Lahore High Court cases, 2006 CLC 463 and 2005 PLD Lah. 428, which,
when taken together, seem to enunciate that whereas an individual has
the right to "seek" education, the Constitution does not
explicitly guarantee any right to "free education". This
appeared to restrict the application of the legal concept to a person
having an equal right to attend an educational institution, subject to
his fulfilling the lawful prerequisites of gaining admission into the
said educational institution, including its financial requirements.
However, the 18th Amendment thereafter enacted Article 25A, which
states: "The state shall provide free and compulsory education to
all children of the age of five to sixteen years in such manner as may
be determined by law". Here the right seems to have been redefined
to include free education.
Although quite laudable, there are several impediments to its
enforcement.
The most problematic part of this clause is the portion which states
that the right to education shall be provided "in such manner as
may be determined by law". At the moment, there seems to be no
defined manner via which one could in fact dispense free education to
the masses, and hence the question arises as to whether Article 25A
would be enforceable in the absence of any explicit legal instrument
delineating a manner of implementing it, as is apparently required by
the said article. If one takes the view that the legislature would have
to enact a legal instrument or legislation to enforce and implement the
said article, the same would amount to rendering the constitutional
article redundant in the meanwhile, and as is well settled, the courts
would never attribute redundancy to any provision of the law.
Furthermore, the word "law" not only constitutes statutory
provisions and legislation, but also judicial principles set down by the
courts of law. Hence, it may very well be the case that where the
government and parliament are seen as failing in their responsibility to
implement the said fundamental right, the court may via various judicial
principles, including that of legitimate expectations and vested rights,
start enforcing it, or at least make an attempt at doing so.
However, if in fact the above-mentioned impediments are resolved,
certain questions still remain. For example, out of the estimated
population of 185 million, children aged between 0-14 years are said to
account for an approximate 40 per cent of the total populace. Hence, the
question as to how the government intends to provide free education to
such a massive demographic as encapsulated by the enumerated age bracket
in Article 25A is yet to be answered. Furthermore, amongst other issues,
the enforceability of the right may open the floodgates with respect to
increased litigation in the high courts and the Supreme Court, further
aggravating an already beleaguered and overworked superior
judiciary.
With that said, nothing stated above takes away anything from the fact
that the enactment of Article 25A is an achievement in itself. It is
fraught with certain difficulties and bottlenecks which perhaps should
have been anticipated and addressed prior to the passage of the 18th
Amendment. The writer is a Karachi-based lawyer.
(By
Basil Nabi Malik, The News, 12/05/2010)
|